Project Display Project Display

Huizhou Jinshan Sewage Project

2023-03-21
分享到:
Project Time: 2019 Scale: civil construction 100000m³/d, equipment according to 100000m³/d; the project covers an area of 47145.6 square meters.


Treatment process:
Pre-treatment process: coarse grating, lifting pumping station, fine grating and aeration and sand sedimentation tank.
Biochemical treatment process: AAO biological tank, secondary sedimentation tank, distribution well and sludge pumping station.
Deep treatment process: intermediate lifting pumping station, denitrification deep-bed filter.
Disinfection treatment process: contact disinfection tank, chlorination and dosing room.
Sludge treatment process: sludge dewatering machine room.